Extra Details
Ukiah Valley And Redwood Valley Water Supply Reliability Intertie And Well Development Project
Objective
Ensure Water Supply Reliability and Quality
Projects Steward Organization Relationship To Project
City of Ukiah
Project Sponsor
City of Ukiah
Funders
California Department of Water Resources, Matching Funds Organization
Other Organizations
County of Humboldt
NCRP Administrative Contact
Kate Reza (kreza@northcoastresourcepartnership.org)
Project Stage
Completed
Duration
2016
CLEAN AND ABUNDANT WATER FOR HUMAN COMMUNITIES
Ensure Water Supply Reliability and Quality
The project provides immediate drought relief and future supply reliability by upgrading three existing and building two new interties to connect six public water systems. Additionally, the project will construct three new wells, providing additional groundwater to diversify the region's available water sources.
Key Accomplishments
- Avoided Costs: $31,200.00
- Community Health and Safety - # of projects: 1 count
- Environmental justice and social equity - # of projects: 1 count
- Jobs created or retained (FTE): 5
- Water supply improved - estimated increased instream flow (acre-feet): 850 acre-ft
- Water supply improved - households impacted: 13,800
Project Types
- Community Health and Safety: Infrastructure Improvements
- Ecosystem Conservation and Restoration: Watershed Enhancement
- Climate Action: Mitigation and Adaptation
1. Installation of monitoring well
Location
Expenditures
Expenditures by Funding Source to Date: $2,226,450.00
Matching Funds (Matching Funds): $672,000
IRWM Prop 84 Drought (DWR): $1,554,450
Photos
2. Replacement well 4 - pump and motor installed (Timing: During)
4. Completed intertie - Calpella/Redwood Valley (Timing: After)
3. Completed monitoring well - Redwood Valley (Timing: After)
Project last updated 6/23/2023